For the discerning owner with a
new house or extensions under
construction.
We offer independent inspections
at critical stages of
construction. If you need
building progress inspections,
ABS inspections are for you.
This service will assist
you with building problems, help
owner builders, assessment of
the standard work carried out or
ass progress claims.
It is a small investment to help
solve a dispute, keep the job
running smoothly or just
reassurance.
While the building is being
constructed there should be an
overseer who is aware of
building requirements to perform
regular inspection and reports,
to ensure that the building is
constructed to your
expectations.
We prefer to work for our clients
interests without causing added
tension or conflict with the
contractor so the building process
is not delayed by problems or
rectification work during its
construction.
RECOMMENDED PROGRESS AND
INSPECTION STAGES
-
Excavation of piers (prior to
concreting).
-
Formwork edge, reinforcement
steel and mesh for the floor
slab/s (prior to concreting).
-
Concrete slab floor with termite
protection certificate varying
treatment is carried out in
accordance with AS3660-1993.
Termite Certificate should be
sought.
-
Foundation brick walls, brick
island piers, damp proof
courses, termite protection and
shields, and timber bearers and
joists.
-
Timber or steel wall and roof
frame (prior to exterior brick
walls, tile or metal roofing).
-
Lockup stage - completion of
building exterior brickwork
etc., (prior to internal ceiling
and wall linings).
-
Roofing
-
Waterproof membranes to wet
areas including external
terraces and decks (prior to
covering with lining or tiling).
-
Internal fix-out joinery and PC
items (prior to painting).
-
On completion of project
-
At completion of defects
liability period.
|